Two questions: is it allowed, and is it safe?
| Question | Where it is set out | What you need |
|---|---|---|
| Is the use allowed at this location? | The municipality’s environment plan (omgevingsplan) | If it does not fit: an environmental permit for an activity outside the environment plan (BOPA), or an amendment to the environment plan |
| Does the building comply? | Besluit bouwwerken leefomgeving (Bbl) | A building that meets the rules for the new use; for a renovation, often also a permit for a technical building activity |
| Can you rent it out like this? | The municipality’s housing and rental bye-laws | Sometimes a conversion, housing creation or rental permit |
| Is it fire-safe in use? | Bbl, use notification | A use notification to the municipality, at least four weeks before occupation |
To see exactly which permit you need, use the permit check in the Omgevingsloket (the national permit portal). If in doubt, call the municipality before you invest.
The environment plan and a temporary permit
Since the Omgevingswet (Environment and Planning Act, 1 January 2024), the environment plan sets out which use is allowed at a location. If it says ‘office’ or ‘business’, living or lodging usually does not fit. The municipality can then deviate from the plan with an environmental permit for an activity outside the environment plan.
- Temporary is possible. A BOPA can also be granted temporarily. According to IPLO, there is no statutory maximum term for this; the municipality sets the term.
- Temporary construction: up to 15 years. A temporary environmental permit for a technical building activity has a maximum of 15 years (IPLO, article 10.23 Omgevingsbesluit).
- Lighter assessment. For a temporary activity, the assessment can be more lenient, with less justification and research than for a permanent deviation (IPLO).
- Municipal policy. Many municipalities have a policy for housing migrant workers with requirements on location, numbers and management. Hollands Kroon, for example, rules out short stay in homes and residential areas.
Source: IPLO, ‘BOPA tijdelijk mogelijk’. A temporary permit expires: allow in your calculations for the use having to stop afterwards, unless the municipality amends the environment plan.
Building requirements: the Bbl
If the use changes, for example from office to residential or lodging use, the rules for existing buildings usually apply to the new use. They only apply to the parts of the building affected by the change (IPLO, ‘Functiewijziging in het Bbl’).
- Existing buildings as the minimum. The level for existing buildings is the minimum; for a renovation, the legally acquired level often applies, with new build as the upper limit.
- New parts. New walls or rooms have no legally acquired level; there, existing buildings are the minimum.
- No lower than it was. In a renovation, quality may not drop below what it was (article 5.5 Bbl).
- Fire safety for residential use. Residential use comes with requirements including smoke alarms along escape routes and self-closing doors.
Have an adviser or structural engineer record which level applies to each part of the building. That is also what the municipality wants to see with the application.
Use notification and renting out
If you rent per room, a fire safety use notification is always mandatory. For lodging use, it depends on the number of people staying at the same time (article 6.6 Bbl). You submit the notification to the municipality at least four weeks before occupation (IPLO, ‘Gebruiksmelding Bbl’).
In addition, the municipality may require a permit for room rental or for renting to migrant workers. See permit for room rental and which permit you need.
How to go about it
- 01
Preliminary consultation with the municipality
Present the plan: how many beds, for whom, for how long, and with what management. Many municipalities have an omgevingstafel (consultation table) or intake.
- 02
Have the building assessed
Fire safety, escape routes, daylight, ventilation and sanitary facilities per room. Use the SNF standard as a guideline for space per person.
- 03
Apply for the permits
Environmental permit via the Omgevingsloket, a rental permit if needed, and then the use notification.
- 04
Arrange certification and management
SNF if you rent to employment agencies, a fixed point of contact and house rules in a language the residents understand.
- 05
Register with Workbeds
Free, via registering as a provider. Workbeds launches on 11 January 2027.
People also ask
May I convert an empty office into housing for migrant workers?
If the municipality allows it. If the use does not fit the environment plan, an environmental permit for an activity outside the environment plan is needed, possibly temporary.
How long may temporary housing in a converted building last?
There is no statutory maximum for a temporary deviation from the environment plan; the municipality sets the term. For a temporary technical building activity, the maximum is 15 years (IPLO).
Does a converted building have to meet new-build requirements?
Usually not. With a change of use, the level for existing buildings is the minimum, and for a renovation the legally acquired level often applies (Bbl, IPLO).
Do I need a use notification?
Always when renting per room. For lodging use, it depends on the number of people. Submit the notification at least four weeks before occupation.
What is flexible housing (flexwonen)?
An umbrella term for temporary forms of housing for people who need a place quickly, such as migrant workers, first-time renters or urgent home seekers. Often in temporary units or converted buildings, with a temporary permit.